Gantt Chart

Gantt Chart

NolaPro Gantt chart showing task bars, milestone diamonds, dependency arrows, and today line

Path: Projects -> Projects → select a project → Gantt (taskbar)

A timeline view of project tasks and milestones.

Chart Layout

  • Left panel: Lists tasks and milestones by name, with subtasks indented.
  • Right panel: Timeline with horizontal bars for tasks and diamond markers for milestones.
  • Today line: A red vertical line marks today's date.
  • Progress fills each task bar based on status; dependency arrows connect related tasks; weekends have a darker background.

Interactions

  • Zoom: Switch between Day, Week, and Month granularity.
  • Today button: Scrolls the timeline to center on today.
  • Critical Path: Toggle to highlight tasks on the critical path in red.
  • Resize bars: Drag the left or right edge of a task bar to adjust its start or due date.
  • Click a bar opens the task editor; hover shows a tooltip with task details.